  • A Week of Change

    This week has seen so much progress! Monday started with the slab pour. It was interesting to watch how the workers smoothed out the poured concrete as well as to see the different texture / seams on the outdoor patio. It was sealed before Tuesday’s rain, which was stressful to see in person, but the…

  • Preparing for the Pour

    As the next week will see a massive change in the project, it is time to provide this overdue update. Over the past few weeks we have seen Foundation walls go up and plumbing go in. We are at the point that the slab pour should be happening on Monday. Lets go back in time.…

  • Getting our Footing

    We pulled ahead of schedule with a fast demolition only to fall back into schedule due to an unknown (yet not unexpected) oil tank found underneath the previous garage. After navigating a couple weeks of permitting, environment testing, and Fire Marshall sign-off, the tank was removed, and the project was moving forward again. And with…